The Senate passed the Bipartisan American Affordability and Jobs Act of 2026 (BAAJA) by a 62 to 33 vote on Thursday, November 19, 2026. Most coverage treats it as a permitting bill. For commercial real estate, the part that matters most is a section titled "Ratepayer Protection," because the BAAJA data center rules would change three things an investor underwrites on any powered site: who pays for the grid, how much capital has to be posted before a utility builds, and whether being early in the utility queue still secures power. The bill is not law. It now goes to the House, with very few legislative days left in the session. For the wider toolkit, see our guide to AI tools for real estate investors.

Key Takeaways

  • The Senate passed BAAJA 62 to 33 on November 19, 2026. It still needs House passage and a presidential signature before any of it takes effect.
  • The bill would add a new Section 229 to the Federal Power Act barring utilities from recovering the incremental cost of serving a data center from any other customer.
  • There is no megawatt threshold in the definition. White & Case reports the substitute amendment removed the 20 megawatt floor that the earlier version carried.
  • States could award power through open seasons or competitive solicitations based on ratepayer benefit, regardless of the order in which requests were received.
  • Sites that interconnect before enactment under a state-approved arrangement are left in place, unless the state chooses to revise the arrangement.

What the Senate Passed and Where It Stands

The Associated Press reported that the Senate approved the bill 62 to 33, with fifteen Democrats voting yes and two Republicans voting no, and that the measure passed without amendments offered by rank-and-file senators. The four lead sponsors are Republican Senators Shelley Moore Capito and Mike Lee and Democratic Senators Martin Heinrich and Sheldon Whitehouse. The AP also reported that President Trump urged approval.

The House is the open question. In its alert on the bill, White & Case noted that as of November 20 there were twelve days left on the House calendar for this session, and that the Speaker has indicated a preference for moving the bill either under suspension of the rules, which requires a two-thirds vote, or under a rule, which requires a simple majority but more process. The firm also reported that a second manager's amendment addressing tribal sovereignty and landowner concerns was blocked before the final vote.

A note on the text used here. The section references and quotations below come from the 494-page manager's substitute amendment that the sponsors released on November 7 and that the Senate Energy and Natural Resources Committee hosts. The House can change any of it, so treat section numbers and deadlines as the Senate's position, not settled law.

The BAAJA Data Center Provisions, Section by Section

The data center material sits in Section 2107, with two smaller companion sections.

A national cost policy and a FERC deadline

Section 2107(a) states that it is the policy of the United States that owners and operators of what the bill calls computational load sites "bear the full cost of any electric service that they require and the full cost of any infrastructure built to serve them, regardless of whether they take the electric service that they request." It then gives the Federal Energy Regulatory Commission 90 days after enactment to revise its 1994 transmission pricing policy statement and issue a proposed rule. The revised policy must require utilities to charge these customers the embedded cost plus "a reasonable assessment" of the incremental cost of transmission service, and it must provide a lower cost of service for customers that elect non-firm transmission service. A final rule is due within one year of the proposed rule, and it covers transmission rates for existing customers as well as new ones.

A federal floor on retail cost recovery

Section 2107(b) adds a new Section 229 to the Federal Power Act. Its core sentence is direct: "No portion of the retail incremental cost may be allocated to, or recovered in the rates of, any customer other than a computational load owner or a computational load operator." Two mechanics follow from it:

  • Recovery continues after exit. Rates and service agreements must be designed to recover the utility's full retail incremental cost, and that recovery continues even if the owner or operator terminates its contract or stops buying power before the cost is paid off.
  • Financial assurance comes first. Before building or upgrading generation, transmission, or distribution facilities needed to serve a site, the utility must require reasonable financial assurances or contributions. Amounts already posted to a public utility or transmission organization for the same site are credited.

Data collection and a toolkit for local officials

Section 2114 directs the Energy Information Administration to revise Form 861 so that computational load sites are reported separately. Section 2117 gives the Department of Energy 180 days to set up a Data Center Community Assistance Program and to publish a plain-English toolkit for local officials. The toolkit must include model questions to ask developers and utilities about infrastructure costs, and the program can analyze projected demand, water use, onsite generation, jobs, and tax abatements on request from a state, local, or tribal government.

No Size Threshold: Which Buildings Count

The bill defines a computational load site as one or more buildings at a single location that primarily contain information technology infrastructure used for software delivery, artificial intelligence training and deployment, cryptocurrency mining, or other computational activity at a data center. No megawatt figure appears in that definition. White & Case reports that the earlier version limited coverage to facilities of 20 megawatts or more and that the substitute amendment eliminated the threshold.

That is a wider net than the other federal efforts. According to the same alert, FERC's show cause orders on large load interconnection targeted single-site loads above 50 megawatts. The House bill discussed below starts at 100 megawatts. Under the Senate text, a small colocation building or an industrial building converted to compute use is inside the definition.

Two limits are worth reading closely. First, the definition excludes computing or data storage equipment that is ancillary to a facility whose primary purpose is some other commercial or industrial activity, so the server room in an office tower or a distribution center does not make that building a computational load site. Second, on the transmission pricing side, the bill leaves the term "eligible computational load customer" for FERC to define by rule or order, so the Commission could still draw lines there. The Section 229 retail floor has no comparable delegation.

Why Queue Position Becomes a Weaker Asset

A large share of the premium on powered land comes from sequence: the site that asked the utility first expects to be served first. Section 229(c) would let a state set that sequence aside. A state may "use an open season or competitive solicitation to allocate among computational load owners and computational load operators the opportunity to obtain and contract for retail electric service, making awards in such manner as returns the greatest benefit to other ratepayers on a net present value basis, notwithstanding the order in which applications or requests for service are received." Each award must state the maximum firm demand in megawatts and the category of transmission service.

The same subsection says a state may also:

  • Charge more than both the embedded and the incremental cost of serving a site, and credit the surplus to other customers.
  • Condition service on the owner or operator procuring, building, or contracting for new generation sufficient to serve the site.
  • Condition service on the site accepting a service category that limits how much energy it can draw, or when.
  • Treat data centers as a separate retail class with rates, terms, and service priorities less favorable than those of other large industrial, manufacturing, or commercial loads.

None of this is mandatory. The bill describes these powers as part of the states' reserved authority over retail electric service, which it "recognizes and confirms" without claiming to create. The practical effect is that the outcome will differ by state, and a commission that already has a large load tariff may go further. Our earlier piece on data center large load tariffs covers how those state rules work today.

Our reading for underwriting: where a state adopts a solicitation, a signed land contract and an early service request no longer settle whether the site gets power. The winning proposal is the one that offers other ratepayers the most, which favors applicants willing to bring generation, accept interruptible service, or pay above cost.

How This Differs From the House Ratepayer Protection Act

The House passed H.R. 9340, the Ratepayer Protection Act, by a vote of 417 to 3 on September 16, 2026. That bill amends the Public Utility Regulatory Policies Act to require state regulators to consider a cost recovery standard for data centers with peak demand of 100 megawatts or more at a single site or campus. States decide whether to adopt it. We covered it in our analysis of the Ratepayer Protection Act.

The Senate text uses the same two mechanics, recovery after exit and up-front financial assurance, but changes their legal character and reach:

  • Floor versus consideration. The House bill asks states to consider a standard. The Senate text states a prohibition on allocating retail incremental cost to other customers.
  • Size. The House bill begins at 100 megawatts. The Senate definition has no minimum.
  • Wholesale side. The Senate text adds a FERC transmission pricing rulemaking with deadlines. For background on where the Commission already stands, see our piece on the FERC data center interconnection orders.
  • Allocation. The open season and competitive solicitation language has no counterpart in the House bill's cost recovery standard.

What It Means by Position in the Deal

These points are our interpretation of the Senate text, not statements from the sponsors.

  • Developers and powered land owners. Financial assurance before construction moves capital earlier in the schedule, and recovery after exit turns a walked-away power request into a continuing liability. Both belong in the development budget and in the downside case.
  • Landlords with data center tenants. The bill reaches both the "owner" and the "operator" of a site. In a leased facility those are different parties, so the lease has to say who posts utility security and who carries exit charges if the tenant defaults or leaves early.
  • Industrial owners weighing conversion. With no megawatt floor in the Section 229 definition, a small conversion does not avoid the rules by staying under a size limit.
  • Owners of everything else. Office, retail, multifamily, and ordinary industrial buildings are the customers the floor is written to protect. The bill does not promise lower bills. It restricts one way that costs could be shifted onto them.
  • Anyone in entitlement. A federal toolkit of model questions on infrastructure cost, water, and tax incentives will give local boards a standard script. Expect hearings to ask for more detail, as boards are already doing in places such as Loudoun County.

What CRE Investors Should Do Before the House Acts

  • Sort sites by interconnection status. The Section 229 floor and the state solicitation authority apply to sites that interconnect on or after the date of enactment. Arrangements a state approved before enactment remain in effect, though the state may revise them where its own law allows. Know which side of that line each site falls on.
  • Reread the power provisions in purchase agreements and leases. Check who posts security to the utility, who bears charges that survive termination, and whether a closing condition tied to a service request still protects the buyer if the state moves to a solicitation.
  • Run a non-firm case. The bill directs FERC to price non-firm transmission service lower and lets states condition service on limited-withdrawal categories. Ask whether the tenant's operations and the lease can tolerate curtailment, and what onsite generation would cost.
  • Watch the state commission, not only Congress. The allocation powers are optional and state by state. A commission docket will tell you more about a specific site than the federal vote count.
  • Get the documents organized. Service requests, will-serve letters, facilities study agreements, and security instruments are scattered across deal files. AI document review can pull the dates, megawatts, and deposit terms into one schedule, a workflow we describe in our guide to AI utility capacity due diligence.

If you want help building that kind of review process for a portfolio or a pipeline of sites, The AI Consulting Network works with CRE investors and operators on exactly this type of document and diligence workflow.

What Is Still Uncertain

The House may amend the bill, pass it unchanged, or run out of time. FERC would still have to define which customers are eligible on the transmission side and what counts as a reasonable assessment of incremental cost. States would decide whether to use the solicitation authority at all. The bill also has organized opposition. The AP reported that major environmental groups oppose it over limits on judicial review and changes to environmental statutes, and the Deseret News reported objections from tribal advocates and a dispute between critics and Senator Lee over whether the bill eases data center siting on public lands. This article is general information, not legal advice. Have counsel review the final text against your specific agreements.

Frequently Asked Questions

Q: Is BAAJA law?

A: No. The Senate passed it on November 19, 2026. It must still pass the House and be signed by the President. White & Case counted twelve days remaining on the House calendar as of November 20.

Q: Does the bill apply to an office building or warehouse with a server room?

A: Not under the Senate text. The definition of a computational load site excludes computing or data storage equipment that is ancillary to a facility whose primary purpose is another commercial or industrial activity.

Q: Would existing data centers be affected?

A: Partly. The retail floor in Section 229 applies to sites that interconnect on or after enactment, and state-approved arrangements made before then stay in place unless the state revises them. The FERC transmission pricing rule, however, is written to reach rates for existing customers once it is final.

Q: Does the bill guarantee lower electricity bills for other commercial properties?

A: No. It bars utilities from recovering the retail incremental cost of serving a data center from other customers and lets states credit any surplus they collect to other ratepayers. It does not set or cap anyone's rate.